Compensation from National Grid

Compensation from National Grid

Author
Discussion

jmn

Original Poster:

954 posts

292 months

Wednesday 2nd April
quotequote all
I have a couple of friends who run businesses where I live.

Both businesses cannot operate at all without an electricity supply.

National Grid are undertaking planned works in their area. They will lose their supply for 6 hours on a Friday (their busiest day of the week) and also the following Tuesday, for a further 6 hours.

They were given 7 days notice of the works.

Is it possible to claim loss of earnings/profits in these circumstances?

4Q

3,540 posts

156 months

Wednesday 2nd April
quotequote all
Can't they hire a generator?

jmn

Original Poster:

954 posts

292 months

Wednesday 2nd April
quotequote all
Thanks. I'll certainly mention it.

netherfield

2,867 posts

196 months

Wednesday 2nd April
quotequote all
Can't claim for a planned outage. Usually the electric people take less time than quoted

Bob-iylho

746 posts

118 months

Wednesday 2nd April
quotequote all
We have this senario quite often, usually a few hours.
We have a generator now for 240v and plan work around losing 3 phase.
As mentioned there is no claim for planned outages, and I'd agree it's usually shorter duration then planned.